State allocates Sh1.1B for Mombasa MGR land acquisition

PS Mohamed Daghar lead a delegation of senior government officials in inspecting the MGR line at the Makupa causeway in Mombasa County

The government has set aside Sh1.1billion for land compensation to pave the way for the completion of the rehabilitation of the Mombasa Meter Gauge Railway (MGR) to link with the SGR terminus in Miritini, Principle Secretary State Department of Transport Mohamed Daghar has said

The Sh4.2billion project that commenced in September 2022 was derailed by land acquisition challenges. The project had stopped at 65 per cent.

The Ministry of Roads and Transport has availed the budget to the National Land Commission, compensation process is expected to start.

“It was supposed to last for 12 months and be completed by August but unfortunately we had a challenge of land acquisition because of the right of way of this project.

 About 1.4 Kilometres had to be acquired and because of that my Ministry has given the money that was needed through Kenya Railways to the NLC said Daghar when he inspected the rehabilitation of the MGR line.

When the project is completed, passengers using the Madaraka Express passenger service train and the seven stations along the Standard Gauge Railway (SGR) arriving or departing from Mombasa can use the MGR line.

“As a government, we are going to give concessions rates to this and you will be ferried all the way regardless of the time you arrive by the train whether it is early in the morning, afternoon or evening,” said PS Daghar.

The second part of the project will involve the rehabilitation of the Mombasa Central Railway Station and the setting up of four mini-stations in Changamwe East, Changamwe West, Miritini and Shimanzi.

This, PS Daghar says, will enhance commuter movement for Mombasa residents who will have an alternative mode of transport thus easing pressure on road transport.

“Commuter rail is part of the Mass Rapid Transit system  (MRT) that the Ministry of Roads and Transport is determined to establish alongside other MRT including the Bus Rapid Transit System (BRT) so that people are moved in a safely and efficient manner and they can save time and other commuter related costs,” added Daghar.

 The PS stated that no entity or person is going to frustrate a government project, the sentiment comes in the wake of a court case by the Mombasa County Government to stop the project over lack of public participation and lack of County approval.

“There is no instruction from government or court that warrants frustration, if a project has fully complied with the law and the due process has been followed,” said the PS.

Related posts

Police Nab Two Suspected Miscreants Captured on CCTV

Coast Region Leaders Urged to join forces to accelerate the issuance of title deeds

Mvita DCC puts criminals on Notice as over 100 are arrested

By clicking "Accept" you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in improving your experience. Read More